STRONGSVILLE, Ohio — Swimmers on the Ehrnfelt Recreation Middle in Strongsville have been navigating the steps to first-flooring locker rooms from the basement-degree aquatics middle since April as a result of the pool locker rooms are closed for renovation.

Carpet runners line the hallways to scale back the probability of slipping as swimmers, some nonetheless moist from the pool, stroll up the steps and down a hallway to the 2 locker rooms that are not beneath development.

All 4 of the locker rooms, on the pool and the primary ranges, ought to have been renovated by now.

The town signed a contract in March with Alabasi Development, Inc. of Cleveland that specified all 4 locker rooms can be accomplished inside one hundred eighty days in change for cost of $662,750. That timeline places the completion date for 4 locker rooms at mid September.

It is now November. None are completed. And a few of the rec middle customers ponder whether the town is getting soaked.

“I’ve misplaced sleep over this challenge,” acknowledged Strongsville Constructing Commissioner Tony Biondillo.

“Like several contractor, you all the time have points. It isn’t completed but and the problems we’re coping with are why it isn’t being completed,” stated Bryan Bogre, director of recreation and senior providers for the town of Strongsville. “It is being handled via the authorized division and the contractor.”

Due to that, officers say they’re restricted in what they will say to the general public whereas negotiations are ongoing. Alabasi gained the contract with the bottom worth in a aggressive bid course of over seven different certified bidders. The contract does have a penalty clause: $1,000 for day by day previous the one hundred eighty-day deadline.

The town’s aim now’s to work with the contractor to get the 2 locker rooms  underneath development completed as quickly as attainable, stated Biondillo. That resulted initially in a plan to have them executed by early October. Now, the goal date agreed to by the contractor is Dec. eight, for the decrease two locker rooms.

TC Architects in Akron designed the renovations, which concerned gutting the locker rooms and putting in all new fixtures, counters, benches and rust-resistant lockers, new flooring drains, accessible showers, tile and portray. They’re additionally constructing a brand new entryway from the pool space to the locker rooms.

Residents who use the pool, in the meantime, are tiring of the moist and chilly stroll to the upstairs lockers.

“I can not inform you how horrible it’s to stroll by means of that place together with your swimsuit on,” stated resident Mindy…